Claims and Contract Disputes

The Civilian Board of Contract Appeals has published its annual report for FY 2023, providing data regarding the number of appeals and contractor success rates at the Board.  The data illustrated a number of noteworthy points — and a few welcome trends — for the contracting community.Continue Reading Contractors Had a Strong Success Rate Before the CBCA in FY 2023

The Armed Services Board of Contract Appeals has issued its annual report for FY 2023, shedding light on how often contractor appeals reach a successful result, and what agencies are most frequently involved in contract litigation.Continue Reading ASBCA Issues Annual Report, Providing Data on How Often Contractors Prevail

Earlier this month, the Federal Circuit provided new guidance on the high burden that the government must carry to terminate a contract for default.  In Dep’t of Transp. v. Eagle Peak Rock & Paving, Inc., the Federal Circuit held that the validity of a termination decision does not depend exclusively on the contracting officer’s reasoning — rather, the government must produce evidence during litigation to prove the contractor’s default under a de novo standard of review.  The Eagle Peak decision illustrates that, absent a threshold showing that the contracting officer’s decision was pretextual, contractors challenging a default decision should focus on developing the “clean slate” record needed to rebut the government’s allegations, rather than disputing the contracting officer’s rationale (or lack thereof) for termination.Continue Reading It Makes No Deference: Fed Circuit Confirms Proper Standard of Review in Default Termination Challenges

Contractors often assume that government auditors have special authority to interpret the Cost Accounting Standards.  That assumption is easy to understand — auditors frequently take the position that there is just one “right” way for a company to do its contract cost accounting, based on how other companies do things.  But contractors should know that CAS is flexible and generally gives them options about how to comply, based on the circumstances of their business.  In short, a contractor’s business judgment matters, and contractors can use it to push back on auditors who take an overly rigid view of CAS.Continue Reading So the Auditor Says You Violated CAS?  Remember, Your Business Judgment Matters When Determining Compliance

With continued inflation putting pressure on the defense supply chain, the Department of Defense (“DoD”) has released guidance encouraging contracting officers to provide mutually agreeable relief to fixed-price contractors facing untenable costs.

DoD’s guidance, dated September 9, 2022 and available at the link here, follows a similar guidance earlier this summer which recommended that contracting officers consider including economic price adjustment clauses in new solicitations.  We previously wrote about that guidance here.Continue Reading DoD Releases Updated Guidance for Firm-Fixed-Price Contractors Grappling with Inflation

In response to industry-wide questions about price adjustments for economic inflation, the Department of Defense (DoD) has released guidance about when and how contracting officers may provide financial relief to contractors working on fixed-price contracts.  The guidance generally discourages contracting officers from granting adjustments under the Changes clause due solely to inflation.  But it does not completely close the door to adjustments, and it offers modest options for fixed-price contracts that contain an economic price adjustment clause.  Moreover, DoD encourages contracting officers to consider inserting economic price adjustment clauses in new solicitations.

This blog post summarizes DoD’s guidance, explains the mechanics of economic price adjustment clauses, and offers views about evaluating other grounds for relief.Continue Reading DoD Releases Guidance on Inflation and Economic Price Adjustments for Fixed-Price Contracts

If a contractor is working on a fixed-price contract, can it charge the government for attorney’s fees to defend a False Claim Act (“FCA”) case related to the contract?

In The Tolliver Group, Inc. v. United States (Fed. Cl. Jan. 22, 2020), the Court of Federal Claims (“COFC”) said the answer was “yes,” if the government was liable for an equitable adjustment under the circumstances.  The decision was welcomed by contractors facing meritless FCA suits, which are often costly to defend even when the relator plainly does not have a case.

But the Federal Circuit has thrown cold water on Tolliver — at least for now.  In a decision last week, the court of appeals vacated Tolliver on jurisdictional grounds, concluding that the legal theory of the COFC’s decision was never presented to the contracting officer for a final decision under the Contract Disputes Act of 1978 (“CDA”), and that the COFC therefore lacked jurisdiction over the contractor’s claim.  The Tolliver Group, Inc. v. United States (Fed. Cir. Dec. 13, 2021).Continue Reading FCA Defendants May Be Able to Recover Attorney Fees Under Their Fixed-Price Contracts, At Least For Now

The FAR explains that the Government must accept or reject work as “promptly as practicable after delivery.”  FAR 52.246-2(j).  But what if the contractor knows its work is not compliant, but has asked the agency for a deviation from the contract’s terms?  A recent decision from the ASBCA provides guidance on this tough but not uncommon issue.
Continue Reading Accepting What You Can’t Change: ASBCA Holds that an Agency Must Accept Non-Conforming Goods After Waiting to Consider a Deviation

Government contractors should take note of the Fifth Circuit’s June 30, 2021 decision in Taylor Energy Co. v. Luttrell, which reaffirmed that contractors can enjoy a broad immunity from third-party liabilities—known as “derivative sovereign immunity,” or “Yearsley immunity.” Yearsley immunity emanates from Yearsley v. W.A. Ross Const. Co., an 80-year-old Supreme Court decision, which established that a contractor is immune when (i) it performed acts pursuant to a valid authorization of Congress and (ii) the contractor did not exceed the scope of that authority.

In Taylor Energy, the court dismissed claims arising out of an oil spill containment project in the Gulf of Mexico. The basic claim in the suit was that the contractor failed to effectively remediate and contain the oil. The Fifth Circuit found that the government: (i) provided direction to the contractor through the statement of work, in the form of “goals” and specific contract deliverables and deadlines; and (ii) periodically met with the contractor and reviewed and approved the work during performance. Based on these core facts, the court held the contractor was immune. The court held that it was irrelevant that the statement of work was “barebones,” and that the contractor—rather than the government—designed certain elements of the remediation effort. Following the Fourth Circuit’s 2018 decision in Cunningham v. GDIT, the Taylor Energy decision is another appellate court victory for contractors in the wake of the Supreme Court reaffirming Yearsley’s core principles in Campbell-Ewald Co. v. Gomez.Continue Reading Fifth Circuit Reaffirms Breadth of Yearsley Immunity For Government Contractors

If your company delivers technical data to the Department of Defense, you should take a close look at the Federal Circuit’s decision issued yesterday in The Boeing Co. v. Secretary of the Air Force.

The Court acknowledged that contractors may retain ownership and other interests in unlimited rights data, and it held that they may take steps to put third parties on notice of those rights.  In particular, the Court held that, in addition to the standard legends required by the Defense Federal Acquisition Regulation Supplement (“DFARS”), contractors may also include a legend notifying third parties of the contractor’s retained rights.Continue Reading Technically Still Yours: Court Holds that Contractors May Mark Unlimited Rights Data with a Proprietary Legend