A recent decision by the Armed Services Board of Contract Appeals found the Navy liable to a commercial crane manufacturer for delay damages. In Konecranes Nuclear Equip. & Servs., LLC, ASBCA No. 62797, 2024 WL 2698011 (May 7, 2024), the Board reiterated the age-old lesson—you have to read the contract—and provided guidance about how to calculate the delay damages. Beyond that, the Board found apparent inspiration for part of its holding in an unlikely source: a classic song by the Rolling Stones.

Case Background
The Navy awarded Konecranes a $62 million contract to construct and deliver four 25-ton general purpose portal cranes for use at the Navy’s Puget Sound Naval Shipyard. The Navy needed the cranes to load food, maintenance parts, and other supplies into the Navy’s nuclear submarines at the shipyard. But after an initial test of one of the cranes identified damage to a luffing drum (a component around which steel ropes are wound to raise or lower the boom), the Navy refused to accept delivery of the cranes.

Konecranes and the Navy offered opposing theories on both the ultimate cause of the damaged drum and the appropriate remedy. In attempting to resolve that issue, a parallel disagreement emerged regarding the contract specifications related to the overall operational life of the drum and its surrounding components. Based upon its reading of the contract materials and incorporated ISO quality standards, Konecranes took the view that the “Navy’s specification require[d] only 3,200 hours of operational life from the luffing hoist components.” In contrast, the Navy asserted that the contract required a useful life closer to 15,000 hours. But as the ASBCA later found, the Navy’s preferred, heightened standard was not incorporated into the terms of the contract. In fact, the Navy acknowledged in contemporaneous internal communications that it had not provided “any usage information or hourly information . . . in the RFP” at all. 

While the parties worked to resolve the specification issue, Konecranes completed its construction of the other three cranes using alternative materials. However, the Navy maintained its view that the luffing components were defective and nonconforming with the contract’s specifications because they had not been designed with a useful life of 15,000 hours. Accordingly, the Navy refused to accept delivery of the completed cranes. As a result, Konecranes incurred additional costs associated with a 17-month delay in the contract delivery schedule. Konecranes’ claim for delay damages included excess transportation costs, space rental fees, and crane maintenance costs totaling around $4.9 million.

The ASBCA’s Holding
After a six-day hearing on entitlement and quantum, the ASBCA issued a decision that included at least two noteworthy components.

First, addressing the parties’ contract dispute, the Board concluded that “Konecranes’ four cranes met the contractual requirements” and that the Navy should have accepted delivery. In so doing, the ASBCA rejected the Navy’s “unreasonable” view that Konecranes was obligated to meet an ISO standard that was nowhere mentioned in the contract. As the Board explained, the contractor delivered products that met the minimum standards spelled out in the contract, and “satisfying a minimum requirement constitutes satisfying the requirement.” In a comment that brings to mind the Rolling Stones, the Board went on to note that: 

Ultimately, Konecranes built its cranes, including its luffing drums, to the ISO standard in the Contract’s specifications. In retrospect, the Navy asserts it did not get what it wanted. But, it got what it contracted for.

Second, addressing Konecranes’ damages, the Board ruled that Konecranes had proven its delay damages for a ~17-month period preceding the hearing, but Konecranes could not recover estimated future costs as part of its partial breach claim. As noted in the decision, Konecranes’ $4.9 million in actual damages fell into four categories: (1) transportation delays, (2) yard costs, (3) crane maintenance costs, and (4) long term storage preparation costs.

Konecranes also sought payment for “estimated future costs” for the period January 2022 through August 2023, which Konecranes had not expected to incur as of the date of the April 2022 hearing. The Board denied recovery for these costs, commenting that they were speculative and “based on assumptions that have not yet come to pass.” As the Board noted, “Konecranes’ president acknowledged that some of the figures for these future costs were ‘purely my guesstimation’ or ‘guestimate[s]’.” Accordingly, the Board declined to award Konecranes the “guestimate” damages amounts, but invited Konecranes to submit new claims in the future for costs “actually incurred.”

Key Takeaways

The ASBCA’s decision serves as a useful reminder of two points.

First, it is the actual language of the contract that governs—not what one of the parties believes the contract should say. When faced with attempts by the government to impose unstated, onerous requirements, contractors can and should object, and contractors should document their position based on the language in the contract. If the government insists on extra-contractual obligations that cause delay and damages, contractors should carefully evaluate the potential to recover such damages.

Second, the Board can award a wide range of delay damages. However, to the extent contractors expect ongoing costs for future delays during the pendency of an appeal, contractors should make every effort to document and support such delay damages with objective data, while recognizing they may be required to submit new claims for those future costs after they are incurred.

Print:
Email this postTweet this postLike this postShare this post on LinkedIn
Photo of Evan R. Sherwood Evan R. Sherwood

Evan Sherwood counsels federal contractors on Contract Disputes Act (CDA) claims, the cost accounting standards (CAS), cost allowability, requests for equitable adjustment (REAs), contract terminations for convenience / default, and related audits, litigations, and investigations. He also advises on contract compliance and formation…

Evan Sherwood counsels federal contractors on Contract Disputes Act (CDA) claims, the cost accounting standards (CAS), cost allowability, requests for equitable adjustment (REAs), contract terminations for convenience / default, and related audits, litigations, and investigations. He also advises on contract compliance and formation issues, including TINA / defective pricing, data rights, mandatory disclosure rules, ethics, conflicts of interest, teaming arrangements, and other transaction agreements (OTAs). He has litigated matters before the Court of Federal Claims, the Armed Services Board of Contract Appeals, and the Government Accountability Office. Evan was partially seconded to Northrop Grumman from 2019 to 2022 as business unit counsel.

In his work for defense and civilian agency contractors, Evan:

  • Prepares CDA claims and REAs;
  • Litigates and counsels on matters involving CAS compliance, cost accounting practice changes, and cost allowability under the FAR and agency supplements;
  • Defends contractors during audits and investigations involving the Defense Contract Audit Agency (DCAA), Defense Contract Management Agency (DCMA), and the Office of the Inspector General (OIG);
  • Advises on constructive changes, work delays, defective specifications, stop-work orders, government-furnished property, CPARS, warranty matters, data rights, and quality controls;
  • Counsels on disputes between primes and subcontractors, including teaming disputes;
  • Conducts internal investigations and defends clients in federal investigations involving whistleblower allegations and retaliation claims.

Evan is a Vice Chair of the ABA Public Contract Law Section’s Contract Claims & Disputes Resolution Committee. He routinely writes and speaks about legal issues in federal contracting.

Photo of Daniel Russell Jr. Daniel Russell Jr.

Dan Russell represents government contractors in complex, high-stakes litigation. Over the past two decades, Dan has served as lead counsel for some of the largest U.S. defense contractors in a broad range of contract disputes and tort claims, including cases valued well in…

Dan Russell represents government contractors in complex, high-stakes litigation. Over the past two decades, Dan has served as lead counsel for some of the largest U.S. defense contractors in a broad range of contract disputes and tort claims, including cases valued well in excess of $100 million.

Dan has experience litigating contract claims and disputes before federal judges and juries, the Boards of Contract Appeals, and the U.S. Court of Federal Claims, including matters arising out of terminations, cost-allowability disputes, defective pricing claims, prime-sub disputes, and claims under the Contract Disputes Act (CDA). Dan has also represented contractors in a myriad of tort suits arising out of work performed for the federal government. Dan has unparalleled experience defending “contractor on the battlefield” tort suits involving contracts performed during wartime or other high-risk, contingency environments. Dan has obtained complete dismissals of tort suits based on an array of federal-law-based defenses, including the government contractor defense, the political question doctrine, federal preemption, and derivative sovereign immunity.

Dan has litigated a variety of other matters involving government contracts and uniquely-federal issues, including: cases brought under the civil False Claims Act (FCA); insurance coverage matters for federal contractors; claims against federal agencies brought under the Administrative Procedure Act and the Federal Tort Claims Act; and regulatory enforcement actions.

At the appellate level, Dan has argued cases before the U.S. Courts of Appeals for the Fourth Circuit, the Fifth Circuit, and the Ninth Circuit. He has also represented clients in matters before numerous other appellate courts and the U.S. Supreme Court.

In addition to his litigation practice, Dan regularly provides risk-mitigation counseling for contractors, with a particular focus on strategies to reduce potential exposure to tort claims and other liabilities in connection with the performance of high-risk government contracts.

Photo of Homer La Rue Homer La Rue

Homer La Rue is an associate in the firm’s Washington, DC office and a member of the Government Contracts Practice Group. Drawing on his experience in industry and at the U.S. Department of Defense (DOD), Homer advises a diverse mix of clients on…

Homer La Rue is an associate in the firm’s Washington, DC office and a member of the Government Contracts Practice Group. Drawing on his experience in industry and at the U.S. Department of Defense (DOD), Homer advises a diverse mix of clients on a broad range of matters related to government contracting, including: complex regulatory compliance matters, high-stakes investigations, enforcement actions, corporate transactions, and prime contractor / subcontractor disputes. Prior to joining the firm, Homer spent over a decade at the Defense Contract Management Agency (DCMA) working in support of key Defense and Intelligence Community buying commands. As a warranted Corporate Administrative Contracting Officer (CACO), Homer’s duties included a wide range of enterprise-wide contract administration and audit resolution functions.

Homer also maintains an active pro bono practice focused on indigent criminal defense.