Tight deadlines are a fact of life in the world of government contracting. Indeed, it is not unusual for the government to expect a contractor to provide large amounts of information in just a few short days. And the draconian penalty for missing such a deadline is usually the rejection of a proposal.
But can an agency’s deadline be unreasonably short? Yes. In MCR Federal, LLC, GAO determined that the agency’s deadline for submitting its final proposal revision (“FPR”) was so short that it deprived the protester of a fair opportunity to improve its proposal.Continue Reading Not So Fast Guy: Recent GAO Decision Provides Rule For When Agency Deadlines Are Unreasonably Short