The Contract Disputes Act (“CDA”) is probably not the first law that comes to mind when a government contractor is named as a defendant in a personal injury or wrongful death suit. But a recent decision from the U.S. Court of Federal Claims illustrates why the CDA ─ and its six-year statute of limitations ─ should be top of mind for any contractor that is sued in tort and wants the government to take over its defense or to reimburse its uninsured legal fees or settlement/judgment costs. The Court’s decision, which is the latest opinion in a long-running dispute, is an important reminder for contractors that are indemnified by the government for liabilities to third persons, including under clauses such as FAR 52.228-7, Insurance ─ Liability to Third Persons (MAR. 1996) and FAR 52.250-1, Indemnification under Public Law 85-804 (APR. 1984).
Continue Reading Time Stops for No One: COFC Reminds Indemnified Contractors to Mind the CDA Statute of Limitations
Contract Disputes Act
CBCA Issues Rare Decision Addressing Government Claim Accrual
The Civilian Board of Contract Appeals (“CBCA” or “Board”) recently published a decision on accrual of government claims for overpayment under the Contract Disputes Act (“CDA”). In the case, United Liquid Gas Co. d/b/a United Pacific Energy v. Gen. Servs. Admin., CBCA 5846, United Pacific Energy (“UPE”) appeals a General Services Administration (“GSA”) final decision seeking overpayments arising under four task orders that were issued under UPE’s GSA schedule contract to provide propane gas.
In its motion for partial summary relief, UPE argued that GSA’s claims for some of those overpayments were time-barred by the CDA’s six-year statute of limitations. The Board sided with UPE, finding that the discrete overpayment claims at issue in the motion accrued when the Government overpaid each corresponding invoice — each of which occurred more than six years before GSA issued its final decision. In doing so, the Board rejected GSA’s argument that the claims did not accrue until the Government issued an audit report discussing the overpayment issue, which occurred less than six years before GSA issued its final decision.
This decision is important because it adds to the limited number of opinions that the Board has published on claim accrual and reinforces established precedent. Our takeaways are below.Continue Reading CBCA Issues Rare Decision Addressing Government Claim Accrual
CBCA Rules Overhaul Finalized: Effective September 17, 2018
On August 17, 2018, the Civilian Board of Contract Appeals (“Board” or “CBCA”) published in the Federal Register its amended Rules of Procedure governing appeals under the Contract Disputes Act (“CDA”). These amended rules: simplify and modernize access to the Board, clarify obligations under certain prior rules, and increase conformity between its rules and the Federal Rules of Civil Procedure (“Federal Rules”). Furthermore, as reflected in the proposed changes issued in the Federal Register in March 2018, the amended rules are intended to “allow the Board to adopt and apply case law applying the relevant Federal Rules, as well as any future amendments to those Federal Rules, without revising the Board’s rules again.”
Our key takeaways are provided below, and a comparison of the Board’s prior and current rules can be found here.Continue Reading CBCA Rules Overhaul Finalized: Effective September 17, 2018
CBCA Proposes Changes to its Rules
[Update: The CBCA’s amended rules will become effective on September 17, 2018. Click here for additional information and our analysis.]
On March 28, 2018, the Federal Register published proposed changes to the Civilian Board of Contract Appeals’ (“Board”) Rules of Procedure regarding appeals under the Contract Disputes Act (“CDA”). These proposed rules indicate that the Board wishes to: simplify and modernize access to the Board, clarify certain rules, and increase conformity between its rules and the Federal Rules of Civil Procedure (“Federal Rules”). Our key takeaways are below, and a side-by-side comparison between the Board’s current and proposed rules can be found here. Interested parties may submit comments by May 29, 2018.
Continue Reading CBCA Proposes Changes to its Rules
Government Contracts 101 Reminder: Certified Claims Must Include a “Signature”
Earlier this Fall, the Armed Service Board of Contract Appeals dismissed an appeal for lack of jurisdiction because the certified claim lacked a proper signature. Appeal of NileCo General Contracting LLC, ASBCA No. 60912 (Sept. 22, 2017). This simple oversight proved decisive. Although this case does not chart a new course in Contract Disputes Act (CDA) jurisprudence, it serves as a helpful reminder that the Board’s jurisdiction hinges on compliance with basic requirements. Failing to meet any of those requirements could have significant consequences.
Continue Reading Government Contracts 101 Reminder: Certified Claims Must Include a “Signature”
Take it To the Limit: CBCA Limits Application of Maropakis Requirement to Initially Submit Certain Defenses to Government Actions as CDA Claims
Ever since the Federal Circuit held in M. Maropakis Carpentry, Inc. v. United States, 609 F.3d 1323, 1331 (Fed. Cir. 2010) that “a contractor seeking an adjustment of contract terms must meet the jurisdictional requirements and procedural prerequisites of the [Contract Disputes Act], whether asserting the claim against the government as an affirmative claim or as a defense to a government action[,]” contractors appealing a government claim or counterclaim have agonized over whether to incur the administrative burden and expense of submitting their potential defenses as a claim under the CDA or risk losing the ability to assert those defenses on appeal. The Civilian Board of Contract Appeals’ (the “Board” or “CBCA”) recent decision in Jane Mobley Assocs., Inc. v. General Servs. Admin., offers some much needed clarity as to what types of defenses must first be raised as claims. CBCA 2878, 2016 WL 73878 (Jan. 5, 2016).
Continue Reading Take it To the Limit: CBCA Limits Application of Maropakis Requirement to Initially Submit Certain Defenses to Government Actions as CDA Claims
Contractor Defeats Government’s Opportunistic Allegations of Fraud
On October 31, 2015, the U.S. Court of Federal Claims (CoFC) in Horn & Associates, Inc. v. United States (No. 08-415C) rejected three fraud-based counterclaims that were filed by the U.S. Government in response to a breach of contract action brought by the plaintiff, Horn & Associates (Horn), through a certified claim under the Contract Disputes Act (CDA). The counterclaims were asserted under the Special Plea in Fraud statute, the False Claims Act, and the CDA, respectively. The CoFC dismissed the claims because the Government could not establish that Horn had intended for its certified claim to deceive the Government.
Horn is a cautionary tale for government contractors that submit certified claims under the CDA. As discussed below, Horn was vulnerable to fraud counterclaims because its certified claim was “prepared and presented [] in an unorthodox and unfamiliar manner,” with a confusing quantification and presentation of damages. Although the CoFC dismissed the counterclaims, its opinion could be limited to its particular facts, which involved an unusually difficult calculation of damages. A lesson to be learned, however, is that government contractors might avoid such confusion (and such opportunistic counterclaims) by having sufficient clarity and transparency in the preparation and presentation of their certified claims.
Continue Reading Contractor Defeats Government’s Opportunistic Allegations of Fraud